Project Delivery Schedule
|
|
|
|
|
Project Delivery Schedule
|
|
|
|
|
|
|
|
|
[Milestone 01] Client Sign-Off Architectural Development Design
|
|
|
|
|
[Milestone 02] Expo General Submission (1st Submission)
|
|
|
|
|
[Milestone 03] Possession of Plot A5 (tbc)
|
|
|
|
|
[Milestones 04] Detailed Design Issued to Client / Commence Procurement
|
|
|
|
|
[Milestone 05] Temp Building Permit Submission
|
|
|
|
|
[Milestone 06] Freight Commences
|
|
|
|
|
[Milestone 07] Receipt of Osaka Temporary Building Permit
|
|
|
|
|
[Milestone 08] Excavation Complete
|
|
|
|
|
[Milestone 9] Foundations Complete/ Steel Super Structure Installation Commences
|
|
|
|
|
[Milestone 10] Steel Super Structure Complete
|
|
|
|
|
[Milestone 11] Watertight Envelope
|
|
|
|
|
[Milestone 12] Secondary Structure Complete/ MEP 1st & 2nd Fix Complete
|
|
|
|
|
[Milestone 13]Public Presentation Fit out Installation Commences
|
|
|
|
|
[Milestone 14] Fit Out & Public Presentation Set-up Complete
|
|
|
|
|
[Milestone 15] MEP Commissioning Complete
|
|
|
|
|
[Milestone 16] Handover to Client
|
|
|
|
|
|
|
[Milestone 18] Mid-way Maintenance
|
|
|
|
|
[Milestone 19] Expo Closes
|
|
|
|
|
[Milestone 20] Façade Cladding Removed
|
|
|
|
|
[Milestone 21] Removal of Foundation
|
|
|
|
|
[Milestone 22] Site Clear & Handover
|
|
|
|
|
|
|
|
|
Performance Bond Renewal Period
|
|
|
|
|
|
|
|
|
|
|
First meetings with Canada Global Affair
|
|
|
|
|
Stage 1: Verification of Project Requirements
|
|
|
|
|
Stage 1: Verification of Project Requirements
|
|
|
|
|
|
|
Architectural Concept Developed
|
|
|
|
|
Guest Visitor Concept developed
|
|
|
|
|
Updated Architectural Concept Issued to Client
|
|
|
|
|
Architectural Concept Design Client Review Period
|
|
|
|
|
Client Comments Received on Concept Design
|
|
|
|
|
Architectural Concept Design and Budget Updated
|
|
|
|
|
|
|
|
|
Working Workshop with Client
|
|
|
|
|
Architectural Concept Design Developed to Reflect Workshop Outcomes
|
|
|
|
|
So&Co Initial Review Period & Validation of Architectural Drawings
|
|
|
|
|
Budget and Engineering Validation [ESG]
|
|
|
|
|
SO& CO Osaka Government Pre Consultation
|
|
|
|
|
Architectural Development issued to client (Canada)
|
|
|
|
|
Preliminary Public Presentation Integrated Design Concept and Visitor Flow
|
|
|
|
|
Budget Aligned to Architectural Development Design Issued to Client
|
|
|
|
|
Client Review on Architectural Development Design
|
|
|
|
|
Client Sign-Off Architectural Development Design + Reference JKFL Document
|
|
|
|
|
Redesign/value engineering
|
|
|
|
|
|
|
Update design based on clients comments
|
|
|
|
|
|
|
Re-budgeting based on updated design & issue (18/10)
|
|
|
|
|
|
|
Client Sign-Off Architectural Development Design
|
|
|
|
|
|
|
Client Review Stage 01 Deliverables
|
|
|
|
|
Preliminary Integrated Design Concept- Pavilion Design
|
|
|
|
|
Preliminary Integrated Design Concept- Public Presentation
|
|
|
|
|
Preliminary Visitor Flow Diagram
|
|
|
|
|
Sustainable and regenerative design features
|
|
|
|
|
|
|
Building and Systems Requirements Report- Preliminary
|
|
|
|
|
BIM Project Execution Plan
|
|
|
|
|
Detailed Budget and cost Breakdown to Align w Project Schedule
|
|
|
|
|
Baseline Project Schedule
|
|
|
|
|
Preliminary Risk Management Plan
|
|
|
|
|
Preliminary Quality Assurance & Control Plan
|
|
|
|
|
|
|
Security Requirements Report- Preliminary
|
|
|
|
|
|
|
Procurement and Disposal Strategy- Preliminary
|
|
|
|
|
Stage 2: Integrated Schematic Design
|
|
|
|
|
Stage 2: Integrated Schematic Design
|
|
|
|
|
|
|
International Participants Meeting
|
|
|
|
|
|
|
|
|
General Architectural Outline Drawings Issued to Client
|
|
|
|
|
General Design Presentation to Client
|
|
|
|
|
Client Review General Architectural Outline Drawings
|
|
|
|
|
Design Works Continue - Revision as per Client Comments
|
|
|
|
|
|
|
Client Sign-Off General Architectural Outline Drawings
|
|
|
|
|
|
|
|
|
Structural Engineering Report Spatial (coordination/outline design)
|
|
|
|
|
Structural Engineering Outline Report Issued
|
|
|
|
|
|
|
|
|
MEP Design (Spatial coordination/outline design)
|
|
|
|
|
MEP Outline Design Issued
|
|
|
|
|
Outline Design (AoR & EoR) Review & Translation
|
|
|
|
|
Outline Design (AoR & EoR) Review & Translation
|
|
|
|
|
Structured Environment Review & Translation of Structural Engineering Design Outline
|
|
|
|
|
So&Co Review Period & Translation of Outline Architectural Drawings
|
|
|
|
|
So&Co Review Period & Translation of Public Presentation Outline Drawings
|
|
|
|
|
So&Co Prepare Documentation for General Design Expo Submission 1
|
|
|
|
|
Approvals / Pre Submission Consultations
|
|
|
|
|
Approvals / Pre Submission Consultations
|
|
|
|
|
Pre-Submission Engagement OSAKA Temporary Building Permit
|
|
|
|
|
Pre-Submission Engagement Expo 2025 Submission 1
|
|
|
|
|
EXPO Submission 1 Document Preparation - REF# 1
|
|
|
|
|
1st Submission of General Approval Package to Expo 2025 - REF#1
|
|
|
|
|
Public Presentation Creative
|
|
|
|
|
Public Presentation Creative
|
|
|
|
|
Public Presentation Design Commence
|
|
|
|
|
Creative brief & brainstorm
|
|
|
|
|
Preliminary Concept - Public Presentation
|
|
|
|
|
Preliminary Concept - Public Presentation
|
|
|
|
|
|
|
Creative Touch base, Preliminary Concept
|
|
|
|
|
|
|
Deadline for Application to Increase Power Supply
|
|
|
|
|
Increase Power Supply Application Result
|
|
|
|
|
|
|
|
|
|
|
Presentation to GAC of Preliminary Concept
|
|
|
|
|
GAC Review of preliminary concept
|
|
|
|
|
|
|
Client Review Stage 02 Deliverables
|
|
|
|
|
Project Scope, Schedule, Quality Assurance and Control and Risk Assessment
|
|
|
|
|
Updated Building and Systems Requirements Report
|
|
|
|
|
Integration of F&B and Retail Concessions
|
|
|
|
|
Updated Procurement and Disposal Strategy
|
|
|
|
|
Schematic Design Presentation
|
|
|
|
|
Room Data Sheets- Preliminary
|
|
|
|
|
Site and Landscape Outline Design
|
|
|
|
|
Architectural Outline Design
|
|
|
|
|
Civil & Structural Outline Design
|
|
|
|
|
Ground Investigation Report
|
|
|
|
|
Mechanical Outline Design
|
|
|
|
|
Electrical Outline Design
|
|
|
|
|
Sustainability "green" design features
|
|
|
|
|
Preliminary Energy Analysis
|
|
|
|
|
Stage 3: Integrated Design Development
|
|
|
|
|
Stage 3: Integrated Design Development
|
|
|
|
|
|
|
Expo Approvals General Design/ 1st Submission - REF #1
|
|
|
|
|
Expo Approvals General Design/ 1st Submission - REF #1
|
|
|
|
|
1st Submission of General Approval Package to Expo 2025 - REF#1
|
|
|
|
|
Expo 2025 General Design Submission 1 - Review Period
|
|
|
|
|
Expo 2025 General Design Submission 1 - Comments Received - Amend in Submission 2
|
|
|
|
|
Expo 2025 General Design/ Submission 1 Approval
|
|
|
|
|
|
|
|
|
Design Freeze of - Fixed Elements
|
|
|
|
|
Detailed Design Updates Rayside - Fixed Elements
|
|
|
|
|
Detailed Design Reviewed by Client - Fixed Elements
|
|
|
|
|
Updates to Detailed Design Following Client Comments - Fixed Elements
|
|
|
|
|
Detailed Design Issued to Client and So&Co - Fixed Elements
|
|
|
|
|
Detailed Design Review & Translation
|
|
|
|
|
Detailed Design Review & Translation
|
|
|
|
|
AOR & EOR Document Preparation - CIAS Building Permit Submission
|
|
|
|
|
|
|
|
|
Structural Engineering Detailed Design
|
|
|
|
|
Structured Environment Review Period & Translation of Structural Engineering Design
|
|
|
|
|
Structural Engineering Detailed Design Issued
|
|
|
|
|
|
|
|
|
|
|
E&M Preparation of Submission Document
|
|
|
|
|
MEP Detailed Design Issued
|
|
|
|
|
NON FIXED Element Design - Interior Fit out
|
|
|
|
|
NON FIXED Element Design - Interior Fit out
|
|
|
|
|
Detailed Design Continues (Client and Rayside) - Non Fixed Elements
|
|
|
|
|
|
|
|
|
Creative Touch Base Meetings Internal (At Regular 2 wk Intervals)
|
|
|
|
|
Creative Touch Base Meetings Internal (At Regular 2 wk Intervals)
|
|
|
|
|
Creative Touch Base Meetings Internal (At Regular 2 wk Intervals)
|
|
|
|
|
Creative Touch Base Meetings Internal (At Regular 2 wk Intervals)
|
|
|
|
|
|
|
GAC Review of preliminary concept
|
|
|
|
|
Receipt of comments from GAC on preliminary concept
|
|
|
|
|
Approval of Preliminary Concept by GAC
|
|
|
|
|
Discussion with GAC - Preliminary outlines of the workshop #1
|
|
|
|
|
|
|
|
|
Internal Preparation and Confirmation of Outline by ESG to GAC via Email
|
|
|
|
|
ESG and GAC: Questions, Comments, and Modifications on the Outline
|
|
|
|
|
Preparation of Stage 3 Project Management Deliverables
|
|
|
|
|
|
|
Interior Design Requirements Report
|
|
|
|
|
Final Building and Systems Requirements Report
|
|
|
|
|
Updated Risk Management Plan
|
|
|
|
|
Updated quality Assurance and Control Plan 50%
|
|
|
|
|
Updated Procurement and Disposal Strategy including list of proposed long lead times
|
|
|
|
|
Preliminary Operations and Maintenance Manual
|
|
|
|
|
|
|
Stage 3 Design Presentation
|
|
|
|
|
Architectural Detailed Design
|
|
|
|
|
Civil & Structural Detailed Design
|
|
|
|
|
Mechanical Detailed Design
|
|
|
|
|
Electrical Detailed Design
|
|
|
|
|
Sustainability "green" design features
|
|
|
|
|
|
|
|
|
|
|
Client Review Stage 03 Deliverables
|
|
|
|
|
|
|
Stage 4 Construction, Fabrication and Production Documents
|
|
|
|
|
Stage 4 Construction, Fabrication and Production Documents
|
|
|
|
|
|
|
EXPO Approvals and Building Permits. - REF# 4
|
|
|
|
|
EXPO Approvals and Building Permits. - REF# 4
|
|
|
|
|
OSAKA - Temporary Building Permit - REF# 2
|
|
|
|
|
OSAKA - Temporary Building Permit - REF# 2
|
|
|
|
|
Temporary Building Permit Submit General Design Plan
|
|
|
|
|
|
|
General Plan Amendments and Final Confirmation
|
|
|
|
|
Submit Amended General Design Plan
|
|
|
|
|
Approval/ Administration Process
|
|
|
|
|
Osaka Authority Approval Window - Temporary Building Permit Issued (1 wk allowance)
|
|
|
|
|
Inspection Body - Building Permit Application
|
|
|
|
|
Inspection Body - Building Permit Application
|
|
|
|
|
Submission for Building Permit Pre-Consultation (CIAS)
|
|
|
|
|
Pre-Consultaion Period - AOR and CIAS Review and Amend Submission
|
|
|
|
|
Pre-Consultaion Period - AOR and CIAS Review and Amend Submission
|
|
|
|
|
OSAKA Building Permit Full Application Submitted
|
|
|
|
|
Building Permit Processing Period
|
|
|
|
|
|
|
Expo Approval - Submission 02 - REF# 3
|
|
|
|
|
Expo Approval - Submission 02 - REF# 3
|
|
|
|
|
Expo 2025 Approval Final Design/ Submission 2
|
|
|
|
|
Expo 2025 Final Design/ Submission 2 - Approval Period
|
|
|
|
|
Expo 2025 Final Design/ Submission 2 Comments Received
|
|
|
|
|
Expo 2025 Final Design/ Submission 2 Amendments to Design per EXPO Comments
|
|
|
|
|
Expo 2025 Final Design/ Submission 2 - Resubmission period (if needed)
|
|
|
|
|
Expo 2025 Final Design/ Submission 2 Approval Received
|
|
|
|
|
Permit to Commence Construction - REF# 5
|
|
|
|
|
Permit to Commence Construction - REF# 5
|
|
|
|
|
Application to Expo Permit to Commence Construction
|
|
|
|
|
Permit to Commence Construction Processing Period
|
|
|
|
|
Permit to Commence Construction Received
|
|
|
|
|
|
|
|
|
Notify Desired Date of Plot Handover
|
|
|
|
|
|
|
|
|
Apply for Permission Remove Soil - deadline 14 days before removal
|
|
|
|
|
NON FIXED Element Design - Interior Fit out
|
|
|
|
|
NON FIXED Element Design - Interior Fit out
|
|
|
|
|
Detailed Design Continues (Client and Rayside) - Non Fixed Elements
|
|
|
|
|
Rayside provides Conceptual drawings to Fit out project manager
|
|
|
|
|
Fit Out PM start the quotation for custom furniture (Outdoor furniture, receptions desks, stage)
|
|
|
|
|
Interior Design Conceptual drawings Issued From Raysite to Fit out PM
|
|
|
|
|
Fit out project manager start the quotation for “off the shelf” furniture
|
|
|
|
|
Rayside make adjustment of design according to quotes
|
|
|
|
|
Presentation to GAC of preliminary Interior design and gathering space furniture
|
|
|
|
|
GAC Comments on preliminary Interior design and gathering space furniture Recieved
|
|
|
|
|
Presentation to GAC of final Interior design and gathering space furniture
|
|
|
|
|
GAC comments on final Interior design and gathering space furniture Recieved
|
|
|
|
|
|
|
|
|
Public Presentation Creative
|
|
|
|
|
Public Presentation Creative
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CTB Meetings Internal - Set design Intention : Internal Workshop
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Concept Development - Public Presentation
|
|
|
|
|
Concept Development - Public Presentation
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Workshop #1 - GAC members attend the workshop
|
|
|
|
|
GAC and ESG to Debrief on Workshop #1
|
|
|
|
|
ESG Share the List of Operational Needs With GAC
|
|
|
|
|
|
|
|
|
AR Content - Creative team - Identification of interactivity intents for WS 2
|
|
|
|
|
AR Content - Creative team - Creation of asset list and aesthetic approach for WS 2
|
|
|
|
|
SOUND DESIGN - Creation of assets list
|
|
|
|
|
Artistic Direction - Creative team - Production of Preliminary WS 2 Storyboard
|
|
|
|
|
Set design : Internal Workshop on set design intentions "
|
|
|
|
|
SET DESIGN - Internal Concept work for preliminary overall set design and scenic elements
|
|
|
|
|
AR TECHNOLOGY - AR Team - Technical tests (Scenic)
|
|
|
|
|
Set design : Internal - Final design of scenic for WS 2
|
|
|
|
|
SOUND DESIGN - Content preparation for WS 2
|
|
|
|
|
AR Content - Internal validation of the asset list for WS 2
|
|
|
|
|
AR Content - AR Team - Assets production for WS 2
|
|
|
|
|
Workshop #2 | Set up and technical tests on site (AR, Scenic, sound, light, content, tracking)
|
|
|
|
|
Lighting Design - Validation of lighting requirements for AR
|
|
|
|
|
Internal Preparation and Confirmation of Outline by ESG to GAC via Email
|
|
|
|
|
ESG and GAC: Questions, Comments, and Modifications on the Outline
|
|
|
|
|
Workshop #2 | Refine concept, prototype of scenic elements and A/V
|
|
|
|
|
Workshop #2 - GAC members attend the workshop
|
|
|
|
|
GAC and ESG to Debrief on Workshop #2 (Including set design intentions)
|
|
|
|
|
Detailed Experience Design Development based on Workshop
|
|
|
|
|
ESG present to GAC a Preliminary Storyboard
|
|
|
|
|
GAC Review of Preliminary Storyline
|
|
|
|
|
Receipt of comments from GAC on Preliminary Storyline
|
|
|
|
|
Concept Development Stage completes
|
|
|
|
|
Scenic Designs and all physical elements in PP presented to GAC for Approval
|
|
|
|
|
GAC review of Scenic Design/Physical Elements
|
|
|
|
|
GAC comments on Scenic Design/Physical Elements
|
|
|
|
|
Scenic Design/Physical Elements modifications if necessary based on GAC comments
|
|
|
|
|
GAC Approval of Scenic Design/Physical Elements
|
|
|
|
|
|
|
|
|
AR Content - Production of AR content for WS 3
|
|
|
|
|
SOUND DESIGN : Preliminary soundscape design
|
|
|
|
|
SOUND DESIGN : Preliminary equipment list
|
|
|
|
|
Lighting Design - Preliminary lighting design
|
|
|
|
|
Lighting Design - Preliminary equipment list and plan
|
|
|
|
|
Fabrication all Scenic Designs and all physical elements in PP
|
|
|
|
|
Finale plans for Workshop 3 (Lighting, IT, Rig, sound)
|
|
|
|
|
Internal Preparation and Confirmation of Outline by ESG to GAC via Email
|
|
|
|
|
ESG and GAC: Questions, Comments, and Modifications on the Outline of Workshop #3
|
|
|
|
|
Workshop #3 | Pre-integration of scenic elements and A/V, Prototype of content
|
|
|
|
|
Workshop #3 - GAC members attend the workshop
|
|
|
|
|
GAC and ESG to debrief on workshop #3
|
|
|
|
|
Presentation to GAC of V1 Storyboard
|
|
|
|
|
GAC Review of V1 Storyboard
|
|
|
|
|
Adjustments on V1 Storyboard following GAC comments
|
|
|
|
|
Presentation to GAC of Final Storyline
|
|
|
|
|
GAC Review of V2 Storyline
|
|
|
|
|
Receipt of comments from GAC on V2 Storyline
|
|
|
|
|
Architectural lighting - FOH and BOH
|
|
|
|
|
Architectural lighting - FOH and BOH
|
|
|
|
|
Presentation to GAC of preliminary Architectural Lighting interior and exterior
|
|
|
|
|
Hanging and integration plan of Architectural Lighting being developed between ESG and Atomic 3
|
|
|
|
|
GAC Comments on preliminary Architectural Lighting interior and exterior
|
|
|
|
|
Presentation to GAC of final Architectural Lighting interior and exterior
|
|
|
|
|
GAC comments on final Architectural Lighting interior and exterior
|
|
|
|
|
ESG confirms and contracts vendors for Architectural Lighting custom and of the shelf elements
|
|
|
|
|
ESG submits the list of rental elements for Architectural Lighting
|
|
|
|
|
Design And Production of Long Lead items - Public Presentation
|
|
|
|
|
Design And Production of Long Lead items - Public Presentation
|
|
|
|
|
Design and Production of Long Lead items
|
|
|
|
|
|
|
AR Content : Production of Final Content
|
|
|
|
|
AR Content : Production of Final Content
|
|
|
|
|
Production of Final Storyboard
|
|
|
|
|
|
|
Final development and production of AV (AR) content
|
|
|
|
|
Presentation to GAC of Final Storyboard
|
|
|
|
|
Artistic direction - GAC Comment on final Storyboard
|
|
|
|
|
Artistic direction - Final Storyboard delivery
|
|
|
|
|
GAC approval of all AV/AR content
|
|
|
|
|
|
|
|
|
SOUND DESIGN - Final equipment list
|
|
|
|
|
Lighting Design - Final equipment list and plan
|
|
|
|
|
SOUND DESGIN - Final soundscape design and content production
|
|
|
|
|
Lighting Design - Final lighting design
|
|
|
|
|
Public Presentation Design Complete
|
|
|
|
|
|
|
Public Presentation- Final Production Documents and Fabrication
|
|
|
|
|
Confirmation of purchased legacy items/ use cladding etc. April
|
|
|
|
|
|
|
|
|
Updated Risk Management Plan Including final list of proposed long lead times
|
|
|
|
|
Updated quality Assurance and Control Plan
|
|
|
|
|
Updated Procurement and Disposal Strategy
|
|
|
|
|
|
|
Draft Operations and Maintenance (O&M) Manual
|
|
|
|
|
|
|
|
|
|
|
Client Review Stage 04 Deliverables
|
|
|
|
|
|
|
Procurement & Fabrication
|
|
|
|
|
Procurement & Fabrication
|
|
|
|
|
|
|
Cladding Perforated Metal
|
|
|
|
|
Cladding Perforated Metal
|
|
|
|
|
|
|
Origin Handling - Checking and Packing
|
|
|
|
|
Civil/ general Contractor works
|
|
|
|
|
Civil/ general Contractor works
|
|
|
|
|
Scope of Works Development
|
|
|
|
|
|
|
Contractor Detailed Design
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contractor Detailed Design
|
|
|
|
|
|
|
|
|
|
|
|
|
Contractor Detailed Design
|
|
|
|
|
|
|
|
|
|
|
|
|
Contractor Detailed Design
|
|
|
|
|
|
|
Scenic Package - Public Presentation
|
|
|
|
|
Scenic Package - Public Presentation
|
|
|
|
|
Scope of Works Development
|
|
|
|
|
GAC Approval of Scenic Design/Physical Elements
|
|
|
|
|
Procurement Scenic element productions
|
|
|
|
|
|
|
Scenic element productions
|
|
|
|
|
Final Touches on Scenic Elements and Shipping Preparations
|
|
|
|
|
|
|
|
|
ESG confirms and contracts vendors for interior design and gathering space furniture
|
|
|
|
|
ESG places all orders related to interior design and gathering space furniture
|
|
|
|
|
|
|
|
|
AR TECHNOLOGY - ESG Final choice of tablet
|
|
|
|
|
AR TECHNOLOGY - Purchase of tablets
|
|
|
|
|
|
|
|
|
|
|
BOH Foundation specials Drawing Sign off
|
|
|
|
|
|
|
|
|
Presentation Foundation Beam Connections Drawing Sign off
|
|
|
|
|
|
|
Presentation Foundation Connections shipping
|
|
|
|
|
Presentation Structure Fabrication
|
|
|
|
|
Presentation Structure Fabrication
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Freight (Phased Shipping Program to be Developed)
|
|
|
|
|
Freight (Phased Shipping Program to be Developed)
|
|
|
|
|
|
|
|
|
Shipment 1- Ring BeModlar am, GF Columns
|
|
|
|
|
Customs and Port Clearance
|
|
|
|
|
Shipment 1 Arrives onsite
|
|
|
|
|
Shipment 2 - Upper steelwork and roof cassettes and lower cladding
|
|
|
|
|
Customs and Port Clearance
|
|
|
|
|
|
|
Shipment 3 - Upper Cladding
|
|
|
|
|
Customs and Port Clearance
|
|
|
|
|
|
|
Public Presentation Structure
|
|
|
|
|
Public Presentation Structure
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Client equipment (CANADA)
|
|
|
|
|
Client equipment (CANADA)
|
|
|
|
|
|
|
|
|
Expo 2025 - Deliver Permanent Electricity Supply
|
|
|
|
|
Expo 2025 - Deliver Tempoary Water Supply
|
|
|
|
|
Expo 2025 - Deliver Rainwater Drainage
|
|
|
|
|
Expo 2025 - Deliver Permanent Data & Comms
|
|
|
|
|
Expo 2025 - Deliver Cold Water Supply _ HVAC
|
|
|
|
|
Expo 2025 - Deliver Water Supply
|
|
|
|
|
Expo 2025 - Deliver Sewage Connections
|
|
|
|
|
|
|
|
|
|
|
Stage 5: Construction, Fit-up and Public Presentation Installation
|
|
|
|
|
Stage 5: Construction, Fit-up and Public Presentation Installation
|
|
|
|
|
|
|
|
|
Site Mobilization- Site Perimeter Fence, Cabins, Survey
|
|
|
|
|
Construction PLACE HOLDERS ONLY)
|
|
|
|
|
Construction PLACE HOLDERS ONLY)
|
|
|
|
|
|
|
|
|
|
|
Trench Excavation - Utilities, Ducting
|
|
|
|
|
Foundations start/ Excavations - inc elevator pit
|
|
|
|
|
Surface Water - Pipework & Trenching
|
|
|
|
|
Fowl Water drainage Pipework & Trenching
|
|
|
|
|
|
|
Foundation Beams Modular Building - Specials
|
|
|
|
|
Foundation Beams Presentation Structure
|
|
|
|
|
|
|
Foundation Beams Modular Building - Specials
|
|
|
|
|
Foundation Beams Presentation Structure
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Modular Building - (6 day week)
|
|
|
|
|
Modular Building - (6 day week)
|
|
|
|
|
Foundation Beams and GF Colums
|
|
|
|
|
|
|
GF Wall Cassettes and 1st floor - Cassets
|
|
|
|
|
GF Windows Doors and fire Life
|
|
|
|
|
1st Floor Colums and Trusses
|
|
|
|
|
Roof Cassets -1st Floor Wall Pannels
|
|
|
|
|
Ancilery Structures - Stairs etc,
|
|
|
|
|
Windows Doors and Fire Life
|
|
|
|
|
Temporary Utilities Connection
|
|
|
|
|
Hot Weather Site Access Contingency
|
|
|
|
|
|
|
Internal Fit-Out Modular Building
|
|
|
|
|
Internal Fit-Out Modular Building
|
|
|
|
|
Modular Accommodation Fit out of General areas
|
|
|
|
|
Executive Areas Base Build Fit-Out
|
|
|
|
|
Conference Area Base Build Fit Out
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sheeting/ Membrane Instalation
|
|
|
|
|
|
|
Sheeting/ Membrane Instalation
|
|
|
|
|
|
|
Sheeting/ Membrane Instalation
|
|
|
|
|
|
|
Sheeting/ Membrane Instalation
|
|
|
|
|
|
|
|
|
Sheeting/ Membrane Instalation
|
|
|
|
|
Cladding and Eternal Finishing
|
|
|
|
|
|
|
Presentation Structure Complete
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MEP Install Commence Modular
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ducting Supply, return, Fresh & Exhaust
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Modular accommodation power supply
|
|
|
|
|
|
|
|
|
|
|
Installation of Main Distribution Boards
|
|
|
|
|
Installation of Sub Main Boards
|
|
|
|
|
|
|
|
|
Main LV Cable Termination
|
|
|
|
|
Sub main Cable Termination
|
|
|
|
|
Switch & Socket Installation
|
|
|
|
|
Emergency Lighting Installed
|
|
|
|
|
|
|
Integration with Mechanical
|
|
|
|
|
|
|
|
|
|
|
|
|
Modular Accommodation Water Supply Connections
|
|
|
|
|
Modular accommodation Drainage Piping, Toilets, kitchens etc
|
|
|
|
|
|
|
|
|
Sanitary-ware Connections
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Containment for Detection
|
|
|
|
|
|
|
|
|
|
|
Fire Interface Panels Installed
|
|
|
|
|
Detection Heads Installed
|
|
|
|
|
|
|
MEP Modular 1st Fix Complete
|
|
|
|
|
MEP Modular 1st & 2nd Fix Complete
|
|
|
|
|
Testing and Commissioning
|
|
|
|
|
|
|
|
|
MEP Insall Commence Presentation structure
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Installation of Main Distribution Boards
|
|
|
|
|
Installation of Sub Main Boards
|
|
|
|
|
|
|
|
|
Main LV Cable Termination
|
|
|
|
|
Sub main Cable Termination
|
|
|
|
|
Switch & Socket Installation
|
|
|
|
|
Emergency Lighting Installed
|
|
|
|
|
|
|
Integration with Mechanical
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ducting Supply, return, Fresh & Exhaust
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Containment for Detection
|
|
|
|
|
|
|
|
|
|
|
Fire Interface Panels Installed
|
|
|
|
|
Detection Heads Installed
|
|
|
|
|
Testing and Commissioning
|
|
|
|
|
MEP 1st & 2nd Fix Complete
|
|
|
|
|
|
|
Authority / Expo Inspections
|
|
|
|
|
Authority / Expo Inspections
|
|
|
|
|
OSAKA Authority Inspection Period
|
|
|
|
|
Apply for Completion of Construction work (User’s Permit) - 2 wk notice
|
|
|
|
|
|
|
|
|
Public presentation commences install
|
|
|
|
|
Fit out and Experience Set-up
|
|
|
|
|
Fit out and Experience Set-up Complete
|
|
|
|
|
|
|
|
|
Testing and Commissioning AVL
|
|
|
|
|
Testing and Commissioning Complete
|
|
|
|
|
Apply for Expo Use Permit - (Public Presentation Construction Completion)
|
|
|
|
|
|
|
|
|
Inspections, Certificates and Permits
|
|
|
|
|
Complete List of Warranty Documents
|
|
|
|
|
|
|
Confirmation that Safety Plans have been submitted to Expo Organizer
|
|
|
|
|
Correct all defects identified prior to soft opening & within warranty period w documentation
|
|
|
|
|
Updated Risk Management Plan
|
|
|
|
|
Updated Procurement and Disposal Strategy
|
|
|
|
|
Updated quality Assurance and Control Plan
|
|
|
|
|
|
|
|
|
|
|
|
|
Client Review Stage 05 Deliverables
|
|
|
|
|
|
|
Stage 6: Operations and Maintenance
|
|
|
|
|
Stage 6: Operations and Maintenance
|
|
|
|
|
|
|
Pavilion Maintenance Training
|
|
|
|
|
Public Presentation Technical Rehearsal
|
|
|
|
|
|
|
|
|
Expo 2025 Operational Period (Maintenance Cover)
|
|
|
|
|
Post Opening Review and Feedback
|
|
|
|
|
|
|
Apply for Permit for Commencement of Demolition/Removal Work
|
|
|
|
|
|
|
|
|
Stage 7: Dismantling, Recycling, Return
|
|
|
|
|
Stage 7: Dismantling, Recycling, Return
|
|
|
|
|
|
|
Removal Client Equipment Commences
|
|
|
|
|
Construction Infrastructure (Hoarding, Cabins, welfare facilities) installed
|
|
|
|
|
Client Equipment packed for shipping
|
|
|
|
|
|
|
Exhibition dismantle and packaging
|
|
|
|
|
|
|
MEP Rental equipment off hired
|
|
|
|
|
Dismantle fit out Material
|
|
|
|
|
Removal of rental wall lining
|
|
|
|
|
Removal of fit-out complete
|
|
|
|
|
Dismantling Façade cladding
|
|
|
|
|
Removal of Membrane and extrusions
|
|
|
|
|
Dismantle Floor cassette systems
|
|
|
|
|
Dismantle Super Structure
|
|
|
|
|
Removal of rental steel plate
|
|
|
|
|
|
|
Removal of utility trenches
|
|
|
|
|
Transportation of fill from storage area to plot
|
|
|
|
|
Groundwork to return site to pre construction condition
|
|
|
|
|
Site Clear & Handover Plot
|
|
|
|
|
|
|
Stage 8: Project Close-Out
|
|
|
|
|
Stage 8: Project Close-Out
|
|
|
|
|
Project Post-Mortem and Final Report
|
|
|
|
|
Post Project Workshop to discuss the overall project and contract (In Canada TBC )
|
|
|
|
|